2016 Main Street Rehabilitation
Project Description
Main Street was reconstructed in 1987 with new concrete pavement, curb and gutter and sidewalks.  The existing concrete roadway has numerous concrete panels that are cracked or offset, and there are a number of panel joints that need to be repaired.  The project limits are Division Street on the south end and the north Village limits on the north end.  The project involves diamond grinding the surface of the road to create a smooth driving surface, replacing damaged concrete panels and panel joints, replacing deteriorating sections of curb and gutter, upgrading curb ramps that do not meet ADA requirements and streetscape improvements.  Proposed streetscape improvements include landscaped islands, bump outs and crosswalks to provide enhanced pedestrian safety, stamped concrete crosswalks, new trees and planters, new street lights, and upgrades to the Village monuments at the north and south ends of Main Street.

Project Funding
The Village has obtained partial funding through the Federal Surface Transportation Program along with Village Funds that will cover the construction costs for the project.  The estimated cost of the project is $681,000 and 80% of the cost will be Federally funded, while the remaining 20% will be paid for by the Village.  The Federal funding match is limited to $681,000.  Any project costs over this amount will be 100% funded by the Village.

 
 Aerial Photo North Main.jpg
Project Schedule
Final Design Plans/Specifications
July 2015
Bidding November 2015
Begin Construction Phase 1 (concrete road repair and diamond grinding) March 2016
End Construction Phase 1 June 2016
Begin Phase 2 (landscape planting and street scape improvements) August 2016
End Phase 2 November 2016
Begin Phase 3 (Streetlight Fixture LED Retrofit)  September 2016
End Phase 3 November 2016
 ** Two way traffic available  during all phases. Phase 2-3 minimal traffic disruption**  

Project Contact:
Dan Pedersen
Project Leader WisDOT
(414)-208-7508

 

Phase 1 Construction

Schedule 
Resident Letter


Weekly Update
Week 1
Week 2
Week 3
Week 4
Week 5

 Public Information
Meeting Presentation
     Proposed Improvements   Corner Plaza Concept
       PIM PPT Cover.jpg               Streetscaping Planset.jpg               Treetops - Thiensville Pocket Park Plaza - reduced.jpg


Phase 1 Construction Timeline  Traffic Study Phase 1 Project Plan Sheets
 Main Street Schedule  Traffic Study      Plan Set
 Phase 2 Draft Landscape Plan    
Landscape Plan     

Whats Your Idea?
Click Here to share your ideas.

Contact The Project Team
For more details or to discuss the project, please contact the Village Director of Public Works, Andy LaFond at 262-242-3720 or , or the Project Manager, Kevin Wagner at 262-542-5733 or .